221 West 57th Street
Midtown-Times Square, Manhattan 10019
Block 1029, Lot 7502Built 2020Height 1550 ftBIN 1090180
27active devices
32active violations
0issued 2 Oct 2026
2025oldest Cat 1 test on file
Get an email when this building changes
Devices
| Device | Status | Last Cat 1 test | Last Cat 5 test | Active violations | Source |
|---|---|---|---|---|---|
| 1E21279Escalator | Active | 10 Sep 2026 | — | 2 active | |
| 1E21280Escalator | Active | 10 Sep 2026 | — | 2 active | |
| 1E21281Escalator | Active | 11 Sep 2026 | — | 2 active | |
| 1E21283Escalator | Active | 14 Sep 2026 | — | 2 active | |
| 1E21287Escalator | Active | 17 Sep 2026 | — | 2 active | |
| 1E21288Escalator | Active | 16 Sep 2026 | — | 2 active | |
| 1E21289Escalator | Active | 16 Sep 2026 | — | 2 active | |
| 1E21290Escalator | Active | 17 Sep 2026 | — | 2 active |
32 more devices are in the full report.
Boilers
| Boiler | Last inspection filed | Report | Defects | Filing status | Source |
|---|---|---|---|---|---|
| 10000205420Y0001Low Pressure | 29 Jun 2026 | Initial | No | Accepted | |
| 10000205421Y0002Low Pressure | 29 Jun 2026 | Initial | No | Accepted | |
| 10000205422Y0003Low Pressure | 29 Jun 2026 | Initial | No | Accepted | |
| 10000207122N0001Low Pressure | 25 Feb 2026 | Initial | No | Accepted | |
| 10000207123N0002Low Pressure | 25 Feb 2026 | Initial | No | Accepted | |
| 10000207124N0003Low Pressure | 25 Feb 2026 | Initial | No | Accepted | |
| 10000207125N0004Low Pressure | 25 Feb 2026 | Initial | No | Accepted | |
| 10000207126N0005Low Pressure | 25 Feb 2026 | Initial | No | Accepted |
Violations since 2023
ViolationIssued 2 Oct 2026Last Cat 1 test on file
Violations in the last two years
| Issued | Violation | Device | DOB says | Status |
|---|---|---|---|---|
14 Nov 2025 | 111425LBLVIO05421 | — | Boiler | Dismissed |
14 Nov 2025 | 111425LBLVIO05420 | — | Boiler | Dismissed |
14 Nov 2025 | 111425LBLVIO05419 | — | Boiler | Dismissed |
10 Oct 2025 | VIO-FTC-VT-PER-202412-0006240 | 1P48955 | Periodic defects: correction not filed | Dismissed |
10 Oct 2025 | VIO-FTC-VT-PER-202412-0004516 | 1P48959 | Periodic defects: correction not filed | Dismissed |
29 Aug 2025 | VIO-FTF-VT-PER-202412-0005104 | 1D354 | Periodic inspection report not filed | Dismissed |
29 Aug 2025 | VIO-FTF-VT-CAT1-202412-0005539 | 1P0992476 | Cat 1 test report not filed | Dismissed |
29 Aug 2025 | VIO-FTF-VT-CAT1-202412-0005538 | 1P0992475 | Cat 1 test report not filed | Dismissed |
29 Aug 2025 | VIO-FTF-VT-CAT1-202412-0005301 | 1P0991232 | Cat 1 test report not filed | Active |
29 Aug 2025 | VIO-FTF-VT-CAT1-202412-0003344 | 1D354 | Cat 1 test report not filed | Dismissed |
86 earlier violations, back to 2023, are in the Compliance Report.
These violations mean DOB had no report on file for that cycle. It is not a finding that a device is unsafe, and the owner may have filed since. Current status on DOB BIS
Guides: what a failure-to-file notice means · how penalties work · boiler annual filing